1. Completion of Automated Meter Reading Infrustructure to lower meter reading costs and enhance meter reading
information. 9/2024
2. Completion of Missouri American Water interconnection upgrade from 6" to 10" to meet the needs of the ever increasing
growth of the district. 12/2024
3. Completion of West Rock Creek Contol Facility to help ensure better water quality 6/2023
4. Completion of 2000 Gallon Per Minute pump station at Brethold Drive needed for the ever increasing population
within the district. 6/2022
5. Completion of Master Study, this is a system wide infrustructure analysis of needed upgrades invovling aging infrustructure and future needs based on historical information and field analysis. 6/2021